, , ,

HS2 tunneling machine completes first mile under the Chilterns

by

Tunnel progress as HS2 completes first mile under the Chilterns: Image of a man walking within the Chiltern tunnel autumn 2021 #28599-2

The first 2,000 tonne tunnelling machine passed the one mile mark this week during the construction of the first tunnels for HS2.

Launched in May, the 170m long Tunnel Boring Machine (TBM) covered the first mile cutting through a mix of chalk and flint beneath the Chiltern hills just outside London.

Also see

The TBM – named Florence – is one of two identical machines excavating the twin ten-mile-long tunnels. A second machine, Cecilia, is a short way behind, with both TBMs expected to break out in around three years’ time.

Article continues below…
Advert

Enjoy more Railway reading in the monthly magazine.
Click here to subscribe & save.

Designed specifically for the geology of the Chilterns, each machine is a self-contained underground factory, digging the tunnel, lining it with concrete wall segments and grouting them into place as it moves forward.

Welcoming the progress, HS2 Ltd Project Client Rohan Perin said: “The 10 mile Chiltern tunnel will take HS2 underneath the hills and safeguard the woodlands and wildlife habits above ground as well as significantly reducing disruption to communities during construction and operation of the new railway.

“Once complete, HS2 will offer low carbon journey options linking London with the major cities of the north and releasing capacity for more freight and local trains on our existing mainlines. It’s great to see how much progress has been made over the summer and I’d like to thank the crew of Florence and all the tunnelling team for their hard work.”

Article continues below…
Advert

The first two TBMs are operated by HS2’s main works contractor, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

A crew of 17 people keep the machines running, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Align Project Director Daniel Altier added: “I am delighted with the progress that Florence has made since its launch in May, with Cecilia not far behind. All the spoil from the TBMs is converted into slurry before being pumped back to our South Portal site, just inside the M25, where it is processed and used for landscaping on site. This is, and will continue to be, a huge logistical challenge, as Florence and Cecilia continue their journey through the Chilterns.

Article continues below…
Advert

“Florence reaching the 1 mile point is a great achievement, however we still have a long way to go.”

Each of the separate northbound and southbound tunnels will require 56,000 precision engineered, fibre-reinforced concrete wall segments – which are all being made at the south portal of the tunnel, next to the M25. During her first mile, Florence and her crew have installed more than 5,500 separate segments, each weighing around 8.5 tonnes.

Approximately 2.7 million cubic metres of material will be excavated during the construction of the tunnels and used for landscaping around the south portal site. Once construction is complete, this will help create around 90 hectares of wildlife-rich chalk grassland habitats. Chalk grassland used to be widespread across the hills of south east England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.

Article continues below…
Advert

In total there will be ten TBMs on the HS2 project – working to create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.

More than 20,000 jobs and over 650 apprenticeships are already being supported by HS2, which is set to transform transport links between Britain’s major cities, free up space on the rail network for more freight and local services and support the UK’s transition to net zero carbon emissions.

The TBM is named after Florence Nightingale, the founder of modern nursing, who spent many years in Claydon, Buckinghamshire where she wrote books on nursing, with the name suggested by students at Meadow High School in Hillingdon. 

For more information, visit the Sir Robert McAlpine website at www.srm.com


Advert
Subscribe to The Railway Magazine
Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.


Article Tags:

About the Author