RAILWAY ARCHIVE 1982: Making Tracks Round Selby – Inside the Great Railway Diversion

by

–

From the November 1982 issue of The Railway Magazine, we revisit the construction of the Selby Diversion, where tracklaying had begun and major bridges were nearing completion. The contemporary report details the engineering work, signalling arrangements and plans for opening the new railway.

RAILWAY ARCHIVE 1982: Making Tracks Round Selby – Inside the Great Railway Diversion
RAILWAY ARCHIVE 1982: Making Tracks Round Selby – Inside the Great Railway Diversion

MAKING TRACKS ROUND SELBY

BRIDGING AND PERMANENT-WAY WORK ON THE SELBY DIVERSION, DUE TO BE OPEN THROUGHOUT IN OCTOBER NEXT

TRACKLAYING started in September on the Selby Diversion, in the Eastern Region of British Railways, the “foundation stone” of which was laid in a ceremony at Hambleton, North Yorkshire, on July 29, 1980, by the Chairmen of British Railways Board, the National Coal Board, the Central Electricity Generating Board and contractors A. Monk & Co. Ltd. (RM October 1980, page 464).


Enjoy more The Railway Magazine reading every month.
Click here to subscribe & save.

The 14 mile (23·5 km)-long Diversion, from Temple Hirst Junction, on the Doncaster – Selby line, to Colton Junction, on the Sheffield – York line, passes under the Leeds – Selby line at Hambleton, to which junction is made by north to east and south to west curves, the track of which is already laid, giving access to the Diversion. The line is being built to allow the East Coast Main Line to bypass the Selby Coalfield, development of which would cause subsidence on the original ECML route.

Bridges and engineering work

Three of the Diversion’s five major bridges are complete and the other two are in their final stages; all 14 public road bridges—13 over the line and one under it—are open, with work complete on many other minor structures, including six culverts, three service bridges and four out of five footbridges—the fifth, at Colton, will be built after track has been laid.

Of the major bridges, the 1,575 ft. (480 m)-long, 26-span Ryther Viaduct over the River Wharfe is complete, as is the bridge over the River Aire at Temple Hirst, where four 80-tonne steel girders, forming the two river spans, were lifted by two cranes from rail bogies onto a prepared “slide path” parallel to the bridge abutments. Using winches, they were brought into line with the abutments, joined together and “launched” across the river. With the third span, formed of concrete beams, added, and the deck ballasted, the bridge was ready for tracklaying.

The deck of the eight-span Selby Dam Viaduct is being waterproofed, and the bridge over the Selby Canal will soon be ready for this final stage of construction. The fifth major structure, the bridge carrying the Leeds – Selby line over the Diversion, was opened to trains in November last.

First of the four 80-tonne girders forming the two river spans of the bridge across the River Aire at Temple Hirst is lifted onto its “slide path” by two rail-mounted cranes. Photo: British Railways
First of the four 80-tonne girders forming the two river spans of the bridge across the River Aire at Temple Hirst is lifted onto its “slide path” by two rail-mounted cranes. Photo: British Railways

Tracklaying and planned opening

About one-third of the route—3¾ miles (6 km) south from Colton and five-eighths of a mile (one kilometre) north from Temple Hirst—has already been ballasted; all 200,000 tonnes of ballast so far delivered has been brought to the site by rail.

When tracklaying was to start in September, work was first to proceed northwards from Hambleton—where tracklaying trains have access to the Diversion—to Colton, where a high-speed junction with the Sheffield – York line will be laid in. The work was programmed to proceed at a rate of about 2,200 yd. (2,000 m) a week, with the junction at Colton being completed within two months. The section southwards, from Hambleton to Temple Hirst, would then be tackled, with the rails expected to be in place by April.

First trains on the new line are due to run over the Colton – Hambleton section from May, and ECML services are scheduled to be using the whole route between Temple Hirst and Colton from October 1983. Maximum speed will at first be 60 m.p.h., rising to 100 m.p.h. by early the following year and to 125 m.p.h. by June 1984, as regular traffic beds in the track.

Signalling and environmental work

Traffic on the Diversion will be controlled from York Signalbox and the line will eventually be incorporated into a York resignalling scheme. Three signalling relay rooms, at Colton, Hambleton and Temple Hirst, are being equipped by the signal contractors, Westinghouse Brake & Signal Co. Ltd. Contractor for the main civil engineering works, which have been carried out to take account of possible future electrification, is A. Monk & Co. Ltd. and the tracklaying is being carried out by BR engineers.

Environmental considerations have not been overlooked and, with the assistance of North Yorkshire County Council and Selby District Council, substantial landscaping and planting and seeding of embankments and road approaches has been carried out to enable the new line and its structures to blend harmoniously with its surroundings.