Lime Street open for business after eight-week blockade

by

REGIONAL and long-distance train services to and from Liverpool city centre resumed on July 30 following a successful eight-week upgrade of Lime Street station.

All of the station’s platforms have been remodelled and some lengthened and widened to create space for longer trains and more passengers.

As well as two new platforms, and wider and longer platforms elsewhere in the station, around 3km of track was replaced during an eight-week blockade at Lime Street. Signalling and overhead line equipment was also replaced by Network Rail. NR

Two new platforms, constructed during an earlier blockade in 2017, have also been commissioned. However, the former platform 1 is now devoid of track, has been renumbered as platform 0, and is restricted access for staff only.

Article continues below…
Advert

Enjoy more Railway reading in the monthly magazine.
Click here to subscribe & save.

In addition, just under 3km of track on the station approaches has been upgraded, with the track layout completely remodelled to increase capacity and reliability, and reduce delays caused by conflicting movements.

Read more in the September issue of The RM – on sale now!


Advert
Subscribe to The Railway Magazine
Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.


Article Tags:

About the Author