THE Department for Transport has granted Network Rail permission to proceed with the much-delayed scheme to increase capacity on the Hope Valley route in Derbyshire.
The upgrade will start in 2019 and take up to three years, after which it will be possible to increase fast Sheffield to Manchester trains from two to three per hour in each direction and double the frequency of Hope Valley ‘stoppers’ to introduce an hourly service.
A new 1,062m-long loop between Bamford and Hathersage will allow fast trains to pass stopping trains and freights, while the Up and Down Dore South Curve will be extended to hold 520m-long freights and the second track through Dore & Totley station, removed in 1985 to save money, will be reinstated.
Enjoy more Railway reading in the monthly magazine.
Click here to subscribe & save.
The work was originally due to be completed in 2018, but deferred by NR to save costs.