SCOTRAIL Alliance has completed the first stage of its work to electrify the Stirling-Dunblane-Alloa route in central Scotland. Overhead power lines between Greenhill Junction, Polmont Junction and Grangemouth Junction to Larbert Junction went live on May 1, with erection of masts and portals advancing quickly between Larbert and Dunblane, and wiring completed on the Stirling to Alloa branch.

No. 156508 stands at Alloa on May 12, awaiting departure with the 15.41 to Glasgow Queen Street. Note the overhead line equipment, which is now completed as far as Stirling. May 15 marked the 10th anniversary of the official reopening of the Alloa branch, which now carries 300,000 passengers a year – twice the original estimate. STUART FOWLER

Passengers on the route have been disrupted by evening and weekend electrification work since September 2016, but all further work will take place overnight, allowing the normal timetable to resume throughout the week. Electric trains are expected to start operating between Edinburgh, Glasgow, Dunblane and Alloa during 2019.

The £120million rebuild of Glasgow’s Queen Street station – also part of the Edinburgh Glasgow Improvement Programme (EGIP) – passed another milestone in May with the extension of platform 1.

Article continues below…
Advert

Enjoy more Railway reading in the monthly magazine.
Click here to subscribe & save.

Read more in the June issue of The RM – on sale now!


Advert
Subscribe to The Railway Magazine
Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.


Article Tags:

About the Author