Merseyrail network closures in preparation for new trains

by

THE Merseyrail third-rail network will see a series of phased engineering blockades take place between October 20 and June 16 next year, in a project to upgrade track and stations for the new Class 777 trains.

Before the Stadler-built EMUs can enter service, track realignment and platform improvements are necessary, requiring 11 separate closures of between nine and 30 days over the coming months.

First to be affected will be the Northern Line, where the Walton to Ormskirk section will be closed from October 20-28.

Article continues below…
Advert

Enjoy more Railway reading in the monthly magazine.
Click here to subscribe & save.
One of the last stations to be rebuilt to accept new Merseyrail Class 777 EMUs will be Green Lane, between Birkenhead Central and Rock Ferry. On March 15, 2017, No. 507023 descends into Green Lane with a Chester to Liverpool James Street service. ROBIN STEWART-SMITH

That will be followed by a closure at Bank Hall, affecting the Southport line, from November 12 until December 16.

Phase 3 sees work switch to the Wirral Line, with another blockade of the city centre loop line and Mersey Tunnel from December 24 until January 1.

Phases 4-6 will affect the Northern Line in January and February, starting with the Rice Lane to Kirkby section on January 5-13, Liverpool Central to Hunts Cross in stages between January 19 and 27, Southport to Hall Road on February 2-10, and Formby to Bank Hall on February 11-24.

Article continues below…
Advert

Read more in the October issue of The RM – on sale now!


Advert
Subscribe to The Railway Magazine
Enjoy more of The Railway Magazine reading every month. Click here to subscribe.

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.


Article Tags:

About the Author